MICHIGAN PROJECT HISTORY #34
|
|
|
|
BIG IRON RIVER CROSSING ROCK BORE
|
|
Who: Undergound Specialists
|
|
Where: Silver City, Michigan
|
|
When: February 2002
|
|
Size: $38K
|
|
|
|
EBI was contracted by Underground Specialists to conduct a crossing of the Big Iron River in Silver City, Michigan.
EBI had to install an 8-inch HDPE water main beneath the Bi Iron River over a distance of 480 feet. The subsurface
consisted of gray slate and basalt. EBI completed the drill out using a Storm 500. The hole was opened to a 12-inch
diameter and the product pipe was installed in four days. Much of the work was done during heavy lake effect snow
events and cold temperatures.
|
|
MICHIGAN PROJECT HISTORY #92
|
|
|
|
|
TRANSMISSION MAIN & WATER MAIN
|
|
|
Who: West Dig Contractors
|
|
Where: Marquette, Michigan
|
|
When: August 2005
|
|
Size: $80K
|
|
|
|
EBI was awarded a subcontract from West Dig Contractors for the installation by directional drilling of a 12-inch
HDPE transmission main and a 6-inch HDPE water main as part of the Transmission Main and Water Main Project in
Charter Township of Marquette, Michigan. The work consisted of installing 1,345 feet of 12-inch HDPE transmission
main in one shot across a wetland and 650 feet if 6-inch water main across a creek.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|