ILLINOIS - PROJECT HISTORY #139
|
|
|
|
JOINT WASTE DISPOSAL FORCE MAIN
|
|
Who: H. Linden & Sons
|
|
Where: Elgin, Illinois
|
|
When: Nov., 2007-Jan., 2008
|
|
Size: $1,600,000.00
|
|
|
|
EBI was awarded a subcontract from H. Linden & Sons for the installation, by drilling, of a 14-inch HDPE
DIPS fprce main and a 8-inch HDPE DIPS force main as part of the Joint Waste Disposal Force Main Project in Elgin,
Illinois. EBI completed the installation of a toal of 26,000 feet of pipe in approximately 35 days using one crew.
To Minimize disturbance to the surface EBI elected to pull in the 14-inch and the 8-inch together. The average
length of the pulls were approximately 1,000 feet.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|